Settlement Consolidation
Consolidation and stabilization of caissons 3AS, 4AS, 5AS and 4SD of the power plant at Isola Serafini – Monticelli d’Ongina (PC).
2000 | 2001
Jet Grouting treatments for soil stabilization under the caissons along Po river - through caissons reinforced concrete structures and various compaction sand layers - 2 overlapping interpenetrated rows - installed 166 Ø 2200 mm columns - maximum depth over 25 m - total about 3.400 m of Jet Grouting treatment - unconfined compressive strength 12÷25 MPa at 28 days.